Industry Guide
Ohio Mechanics Lien Deadlines: The Notice of Furnishing and the 75-Day Affidavit Window
Ohio runs its mechanics lien system off a document the owner records first — the Notice of Commencement — and a document the subcontractor serves in response: the Notice of Furnishing. The affidavit of mechanics lien is then due 75 days after last furnishing on a commercial project, but only 60 days on a residential one. Miss the Notice of Furnishing window and lien recovery can be capped. This guide walks the Ohio Revised Code Chapter 1311 timeline a contractor or sub actually has to run.